Obama Presidential Center Faces $40M Discrimination Lawsuit Amid Rising Costs and DEI Concerns

Construction Challenges Mount at Obama Center
The construction of former President Barack Obama’s prestigious presidential library in Chicago has encountered significant obstacles, despite its initial commitment to diversity, equity, and inclusion (DEI). Most notably, the project now faces a substantial $40.75-million racial discrimination lawsuit while dealing with mounting costs and delays.
DEI Goals and Initial Vision
When the project first launched, the Obama Foundation established ambitious diversity targets for the 19.3-acre development. Specifically, the foundation mandated that:
- 35% of contracts must be awarded to minority-based enterprises (MBEs)
- Construction contracts should prioritize “diverse suppliers”
- The project should set new benchmarks for inclusion in major Chicago construction projects
Financial Challenges and Cost Escalation
However, the project’s financial landscape has changed dramatically since its inception. Consider the following developments:
- Initial budget: $350 million
- Current estimated cost: $830 million (as of 2021)
- Further cost projections remain undisclosed to the public
The $40.75M Discrimination Lawsuit
Background of the Legal Challenge
At the center of the controversy is Robert McGee, an African American entrepreneur and co-owner of II in One Construction. His company, which specializes in concrete and rebar services, has filed a lawsuit against Thornton Tomasetti, the project’s New York-based structural engineering firm.
Key Points of Contention
The lawsuit highlights several critical issues:
- Thornton Tomasetti allegedly modified standards and implemented new rules regarding rebar spacing
- These changes reportedly differed from established American Concrete Institute standards
- The modifications resulted in substantial cost overruns exceeding $40 million
- II in One Construction now faces potential bankruptcy due to these challenges
The Discrimination Claims
McGee’s lawsuit specifically addresses racial discrimination concerns, pointing out that:
- Thornton Tomasetti allegedly undermined the project’s diversity goals
- The firm is accused of making “baseless criticisms and defamatory accusations”
- The lawsuit cites violations of the Civil Rights Act of 1866
Project Impact and Current Status
Construction Timeline
Despite these challenges, the project continues to move forward:
- Original start date: 2018 (delayed)
- Actual construction beginning: 2021
- Expected completion: 2026
Community Concerns
The project has sparked additional controversies within the local community:
- Residents worry about potential displacement due to rising property values
- Environmental activists have raised concerns about tree removal and wildlife habitat destruction
- Various community groups have attempted legal action to block development
The Foundation’s Response
The Obama Foundation maintains its position:
- They are not directly involved in the lawsuit
- Concrete work is largely complete and won’t face delays
- The Foundation pledges to address any verified instances of racist behavior
Looking Ahead
The Obama Presidential Center, once completed, will serve as a multifunctional complex featuring:
- A presidential museum
- Library facilities
- Conference spaces
- Athletic facilities, including an NBA-regulation basketball court
- The Obama Foundation’s headquarters
While the project continues to move forward, these ongoing challenges highlight the complexities of managing large-scale construction projects while maintaining commitment to diversity and inclusion goals.